Development · September 2026

Up to 1,000 homes near Circle C. What was actually approved?

Austin City Council changed the legal capacity of part of Tract 110 on September 24. That makes much more housing possible. It does not mean 1,000 apartments are permitted, designed and ready to break ground.

Zoning parcel
~67.4 acres at 11010 1/2 S. Mopac
Housing cap
1,000 dwelling units on Tract 1
Old office allocation
651,000 SF in the development agreement
Next hinge
Site plan + Traffic Impact Analysis
The short version

Permission changed. The project still has to be designed, reviewed, traffic-tested, permitted and built.

The easiest mistake: reading “approved for up to 1,000 units” as “1,000 units are coming now.” Council approved the legal framework that allows that scale. The city documents still push major site and transportation decisions into the next development stage.

01 : Same meeting, two legal levers

Why the city documents show two different acreages.

There were two related approvals. One amended the broader Circle C development agreement. The other changed zoning conditions on the smaller parcel where the multifamily project would actually be built.

Agenda Item 83

Development Agreement Amendment

246.389 acres

This is the broader Tract 110 legal framework tied to the old Circle C development agreement and Save Our Springs settlement.

Reallocates development density away from office and toward residential uses.
Removes the old South Bay Extension requirement for this tract.
Adds future transportation and parkland obligations tied to development.
Works together with
Agenda Item 92

Zoning Conditions Change

67.432 acres total

This is the smaller zoning area at 11010 1/2 South Mopac: 67.138 acres on Tract 1 plus a 0.294-acre Tract 2.

Multifamily becomes possible under revised conditional-overlay rules.
Tract 1 is capped at 1,000 dwelling units.
Retail is capped at 10,000 SF and impervious cover on Tract 1 at 16.38 acres.

So when one document says roughly 246 acres and another says roughly 67 acres, neither is necessarily wrong. They are describing different legal layers of the same Tract 110 change.

02 : What changed in plain English

This is really an office-to-housing entitlement shift.

The old development agreement carried a large office allocation on this parcel. The September amendment zeros that office allocation and reallocates density toward residential uses, while the zoning ordinance creates the practical 1,000-unit cap on Tract 1.

The land-use shiftLegal capacity, not a site plan
Office
651,000 SF allocated in the prior development agreement
→
0 SF office allocation in the amended agreement
Housing
Residential capacity existed only at a much smaller scale in the old allocation
→
Up to 1,000 dwelling units on Tract 1 under the new zoning cap
Retail
Roughly 10,000 SF remained in the development agreement
→
10,000 SF maximum under the zoning ordinance for Tract 1

The important distinction: the development agreement uses legacy density-allocation categories, while the zoning ordinance separately says development of Tract 1 may not exceed 1,000 dwelling units. That 1,000-unit ceiling is the cleaner number for understanding the actual development parcel.

03 : Permission is not a finished project

Here is where the project actually sits.

The September vote moves Tract 110 through the land-use gate. The steps that determine what gets built, how it is accessed and when it opens are still downstream.

01 · Done
Development agreement amended
Council authorized the new density, transportation and parkland framework for Tract 110.
02 · Done
Zoning conditions changed
The roughly 67.4-acre zoning area can now support multifamily development, with Tract 1 capped at 1,000 dwelling units.
You are here: the land can support the idea, but the project details still have to clear development review
03 · Next
Site-development permit
The actual layout, drives, buildings, internal circulation and other site details move into city review. Approval of the zoning case does not guarantee driveway locations.
04 · With first site plan
Full Traffic Impact Analysis
The agreement requires a TIA concurrent with the first site-development permit. That study has to examine the La Crosse/Dahlgreen signal, traffic-reduction measures, a shared-use path and driveway access.
05 · After analysis
Transportation decisions + permits
Austin Transportation and Public Works determines the required Dahlgreen access configuration and whether the signal or shared-use path is warranted. Those obligations tie into later permits and certificates of occupancy.
06 · Later
Construction + occupancy
Only after the project clears the remaining review, financing, permitting and construction steps do the approved units become actual homes.
04 : The traffic question

The city deliberately pushed the hardest access decisions to the site-plan stage.

Traffic was the most visible neighborhood concern, but the September approval did not lock every driveway or traffic-control decision. Instead, it created a process for deciding them later with a full TIA.

01

La Crosse + Dahlgreen signal

The TIA must study whether a traffic signal is necessary. If Austin Transportation and Public Works determines it is warranted, the landowner must fully fund and construct it before the first certificate of occupancy.

02

Dahlgreen traffic reduction

The TIA must evaluate traffic-reduction solutions for Dahlgreen Avenue rather than assuming unrestricted neighborhood access.

03

Shared-use path

The TIA must study a shared-use path along Dahlgreen. If required, the landowner must dedicate the needed land before the first certificate of occupancy.

04

Driveway access

The TPW Director will determine the access requirement after the TIA. The agreement lists emergency-only access first, then egress-only, then time-restricted access as potential outcomes.

What disappeared

The old requirement for the property owner to build the South Bay Extension on Tract 110 was removed.

What replaced it

A later transportation review tied to the actual site-development permit, with the TIA and TPW Director determining what improvements and access controls are required.

What is already hard-wired

If required by the TIA, certain improvements must be completed before the first certificate of occupancy. The agreement also requires on-site parkland and a public trail network, including access to Valor South Austin Public Charter School.

05 : Your context

What are you actually trying to figure out?

The same rezoning means something different if you live next door, use Dahlgreen every morning, own in Circle C or are considering moving there.

The zoning vote is not the last local decision.

The next useful records are the site plan, Traffic Impact Analysis and TPW access determination. Those documents will tell you much more about actual circulation, entrances and required improvements than the 1,000-unit headline does.

Watch Dahlgreen at the site-plan stage.

Access is still conditional. The approved agreement requires the TIA to study Dahlgreen and gives TPW several possible access configurations. The actual operating pattern is not fully settled yet.

Do not treat the approval as a finished neighborhood condition.

If you are comparing Circle C homes, this is future context, not a current built condition. Today you still need to evaluate the actual home, route, school assignment, taxes, insurance and current traffic pattern separately.

One rezoning does not equal a property-value answer.

The change may affect future housing supply, traffic patterns and nearby amenities, but none of that translates cleanly into a specific home's value. Watch execution and compare actual market data as the project gets more concrete.

The next signal is not another zoning headline.

Follow site-plan filing, the full TIA, access determinations, parkland/trail plans, permits, ownership changes and construction financing. Those are the steps that convert entitlement into a physical project.

06 : Headline vs. reality

Four shortcuts that make this story sound simpler than it is.

“Austin approved 1,000 apartments.”Closer: Austin approved the legal capacity for up to 1,000 dwelling units on Tract 1.+
That is a meaningful approval, but it is still an entitlement. The actual project must still clear site-plan review, transportation analysis, permits and construction.
“The land was rezoned to an apartment district.”The base zoning labels stayed CS-MU-CO and GO-MU-CO. The conditional-overlay rules changed.+
That sounds technical because it is. The development value sits in the changed conditions: multifamily use becomes available and the permitted intensity changes even though the base zoning abbreviations remain the same.
“Dahlgreen access is already decided.”The old prohibition was removed, but the final access configuration is still tied to the TIA and TPW decision.+
The agreement lays out possible access outcomes and a decision process. It does not simply say “full unrestricted access.”
“So this is about to start construction.”The sources reviewed here do not establish an approved site plan or construction start.+
The zoning and agreement changes are important because they make the project legally possible at a much larger residential scale. Delivery timing remains a separate question.
07 : What would make this materially more real?

Watch these records next.

01
Site-development permit
This is where the conceptual entitlement starts turning into an actual layout, drives, buildings and phasing.
02
Traffic Impact Analysis
The TIA is required with the first site-development permit and becomes the evidence behind the Dahlgreen, signal and shared-use-path decisions.
03
Ownership / execution
Stratus Properties is in an approved plan of liquidation and asset sales. That does not cancel the entitlement, but it makes future ownership and execution worth watching rather than assuming the current corporate structure will build the project exactly as proposed.
04
Permits + construction
Building permits, site work and financing will tell us when this moves from legal possibility into something residents can actually see on the ground.
08 : Common questions

FAQ

Did Austin approve construction of 1,000 apartments? +
Austin approved zoning and development-agreement changes that make up to 1,000 dwelling units possible on Tract 1. That is not the same as an approved site-development plan or building permit.
Why do the documents say both 246 acres and about 67 acres? +
The approximately 246.389 acres refers to the broader Tract 110 development-agreement framework. The zoning case changes conditions on a smaller property made up of 67.138 acres plus 0.294 acre, or about 67.432 acres total.
Is Dahlgreen Avenue access final? +
No. The approved agreement requires a full TIA with the first site-development permit. TPW then determines the access requirement. The agreement lists emergency-only, egress-only and time-restricted access among the options it must consider.
Is the South Bay Extension still required? +
No. The September amendment removes the old South Bay Extension requirement and replaces it with a transportation review tied to the future site-development process.
Is affordable housing required? +
The applicant's July 2025 summary proposed a requirement tying at least 10% of habitable square footage to households at or below 80% of median family income. The September 18 draft development agreement reviewed for this page does not contain that affordability language, so Realty Haus is not treating it as a confirmed final condition without a later executed document that includes it.
Is Stratus still expected to build it? +
Stratus Properties is in a shareholder-approved liquidation process involving the sale of assets and eventual dissolution. The entitlement can remain valuable even if ownership changes. The current sources do not establish who will ultimately own or build the project at construction.
Primary sources + reporting
  • City of Austin, Sept. 24, 2026 Council agenda: Items 83 and 92 for the Tract 110 development-agreement and zoning actions. Council record.
  • City of Austin draft zoning ordinance: 67.138-acre Tract 1 plus 0.294-acre Tract 2, 16.38-acre impervious-cover cap, 10,000 SF retail cap and 1,000-dwelling-unit cap. Draft ordinance.
  • City of Austin draft Fourth Amendment: office-density reallocation, TIA requirements, Dahlgreen access process, parkland and trail requirements. Development agreement.
  • Applicant summary letter: July 2025 explanation of the requested land-use shift and proposed affordability language. Applicant summary.
  • Austin Business Journal, Sept. 25, 2026: reporting on Council approval and the potential 1,000-unit project. Source article.
  • Stratus Properties / SEC: 2026 plan of liquidation, asset sales and voluntary delisting. SEC filing.

Framing note: This page explains land-use and development records. It does not predict whether all 1,000 units will be built, when construction will begin, or how a future project will affect a particular home's value. Project documents can change as later permits are filed and approved.